AIP Supplement for Singapore

Civil Aviation Authority Singapore

AIRAC AIP SUP

102/2020

Effective from 03 DEC 2020

 / 19 MAY 2021

Published on 22 OCT 2020

SINGAPORE CHANGI AIRPORT - CLOSURE OF RUNWAY 02C/20C DUE TO CHANGI EAST DEVELOPMENT WORKS

1 INTRODUCTION

1.1 This AIP Supplement informs aircraft operators and pilots that Runway 02C/20C at Singapore Changi Airport will be closed with effect from 03 December 2020 0000UTC to 19 May 2021 2359UTC for the next phase of Changi East Development works.

2 CONSTRUCTION ZONES AT RUNWAY 02C/20C FOR CHANGI EAST DEVELOPMENT WORKS

2.1 Please refer to Annex A for the location of the construction work zones.

2.2 The work site, which is adjacent to TWY EP, will be demarcated by barricades and supplemented with visual aids.

3 CLOSURE OF RUNWAY 02C/20C

3.1 Runway 02C/20C will be closed for the entire period covered by this AIP Supplement for construction works.

3.2 There will not be any other scheduled maintenance closures and inspections on Runway 02C/20C during the above-mentioned period.

4 MARKING AND LIGHTING

4.1 White runway closed markings will be displayed on the pavement surface at intervals along the entire length of the closed runway, except where the pavement surface is under construction. In addition, a flashing white lighted cross will be placed at each end of the closed runway. Approach and runway lighting will cease to operate.

4.2 All unserviceable areas on taxiways connected to the closed runway will be marked with yellow closed markings and demarcated by low barricades painted in alternate bands of red and white. The barricades will have omni-directional fixed red lights that will be lighted at night and in low visibility conditions.

5 PRECAUTIONS

5.1 During the construction period, pilots are to take note of the following:

  1. Presence of a large area that is under construction in the aerodrome.

  2. Emergency response and evacuation plan for operational areas outside the construction work zones will be available for any airport emergency.

6 CHANGES

6.1 Any change to the contents of this AIP Supplement will be notified through NOTAM.

7 CONSULTATION

7.1 Please write to caas_singaporeais@caas.gov.sg if you have any queries regarding this AIP Supplement.

Location of the construction work zones
PDF